Agile Planning

Planning to be Agile: Destination Unknown

Deadlines:

“I love deadlines… I like the whooshing sound they make as they fly by”. – Douglas Adams

  • How do you avoid this?

    Plan iteratively:

  • Don’t decide everything at the point when you know the least
  • Plan for what you know
  • Adjust as you know more
  • Your estimates will be more accurate

Agile Roles and the Need for Training

Formulas for failure:

  • Product manager becomes product owner
  • Project manager becomes scrum master
  • Developers (alone) become scrum team

Product Manager vs. Product Owner:

Agile Planning

Project Manager vs. Scrum Master:

Agile Planning

Development Team vs. Scrum Team:

Agile Planning

“Until and unless business leaders accept the idea that they are no longer managing projects with fixed functions, timeframes, and costs, as they did with waterfall, they will struggle to use agile as it was designed to be used.”

— Bob Kantor, Founder Kantor Consulting Group, Inc.

The roles have changed:

  • You cannot put people in new roles without the proper training and mindset
  • This mindset must come down from upper management

Kanban and Agile Planning Tools

Agile planning tools:

  • Tools will not make you Agile
  • Tools can support your Agile process
  • Many Agile planning tools
  • ZenHub is one of them

    ZenHub:

  • Plug-in to GitHub
  • Provides a kanban board and project management reporting
  • Customizable and integrated with GitHub

    Why use ZenHub?

  • Helps you manage where you are in a project based on GitHub Issues
  • Provides an easy way to let management know how you are doing
  • Maintains up-to-date status due to integration with GitHub
  • Allows developers to only use one tool – GitHub

What is Kanban Board?

Agile Planning

Real World Example:

Agile Planning

Default ZenHub pipelines:

Agile Planning

User Stories: Creating Good User Stories

What is a user story?

A user story represents a small piece of business value that a team can deliver in an iteration.

Story contents:

Stories should contain:

  • A brief description of the need and business value
  • Any assumptions or details
  • The definition of “done”

    Story description:

  • User stories document a persona requesting a function to achieve a goal:

    As a <some role>

    I need <some function>

    So that <some benefit>

    Assumptions and details:

    It’s important to document what you know;

  • List any assumptions
  • Document any details that may help the developer

    Acceptance criteria:

  • It is critical to document the definition of “done”
  • I like to use the Gherkin syntax

    Given <some precondition>

    When <some event happens>

    Then <some outcome>

    Sample Story:

Agile Planning

Bill Wake’s INVEST:

  • Independent
  • Negotiable
  • Valuable
  • Estimable
  • Small
  • Testable

    Epic:

  • A big idea
  • A user story that is bigger than a single sprint
  • A user story that is too big to estimate on its own

    When to use an epic?

  • When a story is too large in scope it is considered an epic
  • Backlog items tend to start as epics when they are lower priority and less defined
  • For sprint planning, epics should be broken down into smaller stories

Effectively using Story Points

What are story points?

Story point;

  • A metric used to estimate the difficulty of implementing a given user story
  • An abstract measure of overall effort

What does a story point measure?

Agile Planning

Relative T-Shirt sizes

  • Story points acknowledge that humans are bad at estimating time-to-completion
  • Instead, story points use relative T-Shirt sizes (S, M, L, XL)
  • Most tools use Fibonacci numbers (1, 2, 3, 5, 8, 13, 21)

    Agree on what “medium” means:

  • Since story points are relative, it’s important to agree on what “medium” is
  • Then, evaluate from there
  • Is it the same, larger, or smaller than medium

    Story size:

  • A story should be small enough to be coded and tested within a single sprint iteration – ideally, just a few days
  • Large stories should be broken down into smaller ones

    Story point antipattern

  • Equating a story point to wall-clock time
  • Humans are bad at estimating wall-clock time
  • Don’t do it!

Building the Product Backlog

Steps in the Scrum process:

Agile Planning

Product Backlog:

  • A product backlog contains all the unimplemented stories not yet in a sprint
  • Stories are ranked in order of importance and/or business value
  • Stories are more detailed at the top, less detailed at the bottom

Sample requirements:

  • What: A service for counting things
  • Must allow multiple counters
  • Counters must persist across restarts of service
  • Counters can be reset

ZenHub Kanban board:

Agile Planning

Creating new stories

Agile Planning

Story Template:

As a <some role>

I need <some function>

So that <some benefit>

Need a service for counting things:

As a User

I need a service that has a counter

So that I can keep track of how many times something was done

Creating the next story:

Agile Planning

Must allow multiple counters:

As a User

I need to have multiple counters

So that I can keep track of several counts at once

Creating the next story:

Agile Planning

Persist counters across restarts:

As a Service Provider

I need the service to persist the last known count

So that users don’t lose track of their counts after the service is restarted

Creating the last story:

Agile Planning

Counters can be reset:

As a System Administrator

I need the ability to reset the counter

So that I can redo counting from the start

Stories in the backlog:

Agile Planning

Prioritize the product backlog:

Agile Planning

The Planning Process

Backlog Refinement: Getting Started

Backlog refinement:

  • Keep the product backlog ranked by priority so that the important stories are always on the top
  • Break large stories down into smaller ones
  • Make sure that stories near the top of the backlog are groomed and complete

    Backlog refinement meeting:

    Who should attend?

  • Product owner
  • Scrum master
  • Development team (optional)
    • Lead developer/architect

      What is the goal?

  • Groom the backlog by ranking the stories in order of importance
  • Make sure the story contains enough information for a developer to start working on it

Backlog refinement workflow:

Agile Planning

New issue triage:

  • Start with new issue triage
  • Goal: At the end of backlog refinement, the New Issues column is empty

    Take stories from new issues and…

  • Move them into the product backlog if they will be worked on soon
  • Move them into the icebox if they are a good idea but not now
  • Reject them if they are not where you want to go

Agile Planning

Backlog refinement workflow:

  • Product owner sorts the product backlog in order of importance
  • The team may provide estimates and other technical information
  • Large vague items are split and clarified
  • The goal is to make the stories “sprint read”

Complete the story template:

As a <some role>

I need <some function>

So that <some benefit>

Assumptions and Details:

<anything you already know>

Acceptance Criteria:

Given <some precondition>

When <some event>

Then <some measurable outcome>

Need a service that has a counter:

Agile Planning

Must Persist counter across restarts:

Agile Planning

Deploy service to the cloud:

Agile Planning

Ability to reset the counter:

Agile Planning

Backlog Refinement: Finishing Up

Label:

  • Help visualize the work

Labels in GitHub

Agile Planning

Need a service that has a counter:

Agile Planning

Must persist counter across restarts:

Agile Planning

Deploy service to the cloud:

Agile Planning

Ability to reset the counter:

Agile Planning

Technical debt

  • Technical debt is anything you need to do that doesn’t involve creating a new feature
  • Technical debt builds up when you take shortcuts, but may also occur naturally

    Examples of technical debt:

  • Code refactoring
  • Setup and maintenance of environments
  • Changing technology like databases
  • Updating vulnerable libraries

Backlog refinement Tips

  • You should refine the backlog every sprint to ensure the priorities are correct
  • Have at least two sprints’ worth of stories groomed
  • The more time you spend refining the backlog, the easier sprint planning will be

Sprint Planning

  • The purpose of sprint planning is to define what can be delivered in the sprint and how that work will be achieved
  • This is accomplished by producing a sprint backlog

Sprint planning meeting

Who should attend?

  • Product owner
  • Scrum master
  • Development team

    Sprint planning goals:

  • Each sprint should have a clearly defined business goal
  • The product owner describes the goal and product backlog items supporting it
  • It’s important for the whole team to understand why they are building the increment

    Mechanics of sprint planning

    The development team;

  • Takes stories from the top of the product backlog and assigns them to the sprint backlog
  • Assigns story points and labels
  • Ensures each story contains enough information for a developer to start working on it
  • Stops adding stories when the team’s velocity is reached

    Team velocity:

  • The number of story points a team can complete in a single sprint
  • This will change over time as the team gets better at estimating and better at executing
  • The velocity is unique to the team because the story point assignment is unique to the team

    Create a sprint milestone:

  • Create a sprint milestone to start the sprint
  • The milestone title should be short
  • The description should document the milestone goal
  • The duration should be 2 weeks

Create a milestone:

Agile Planning